Project Progress Update (April – June 2020)
20779
post-template-default,single,single-post,postid-20779,single-format-standard,bridge-core-3.0,qodef-qi--no-touch,qi-addons-for-elementor-1.6.3,qode-page-transition-enabled,ajax_fade,page_not_loaded,,overlapping_content,qode-theme-ver-28.4,qode-theme-bridge,disabled_footer_top,qode_header_in_grid,wpb-js-composer js-comp-ver-7.1,vc_responsive,elementor-default,elementor-kit-21820

Project Progress Update (April – June 2020)

Project Progress Update (April – June 2020)

All 4 sites – Dwi@Rimbun Kasia, Rimbun Kasia Central, KaMi and ASTA Enterprise Park are now open – our project staff have worked hard to get each site ready for construction to re-start, preparing documents to submit to Government agencies like CIDB and the relevant local authority. The health and safety of all site workers is our priority, so we prepared markers for social distancing, setting out sanitizer and temperature check stations, and general cleaning of the sites. Testing on the workers started in May, and we are pleased to report that all the results have come back negative. All our sites are now fully open.

Dwi and Kami

Pic: Dwi@Rimbun Kasia (Left), KaMi Mont’ Kiara (Right)

Dwi@Rimbun Kasia

Structural works for Block A (West Wing) is at Level 4. This is 100% completed and 50% completed at Level 5.

Structural works for Block B (East Wing) at Level 4 is 100% completed. It is 60% complete at Level 5 and 30% at Level 6.

Architectural works are completed at Block B, Level 1 and works at Level 2 are currently in progress.

Rimbun Kasia – Central Park

The main contractor is carrying out preliminary works such as checking the existing levels and demarcating the work area, with a view to starting work on this soon.

KaMi Mont’ Kiara

Currently reinforced concrete works are in progress, with Levels 3, 4 and 5 at 100% completion.

2 out of 7 zones are completed at Level 6, and 2 out of 5 zones are completed at Level 7.

ASTA Enterprise Park

The Movement Control Order (MCO) delayed project progress for Phase 1 and therefore a revised work programme has been drafted for building the 18 Semi-Detached Factory (Type A) units. Phase 1 is now targeted for vacant possession in October 2020.

Earthworks have started on Phase 2 (also 18 Semi-Detached Factory (Type B) units) and building works will commence as soon as this is completed. The project is scheduled to be completed by June 2022.