Project Progress Update (April – June 2021)
21542
post-template-default,single,single-post,postid-21542,single-format-standard,bridge-core-3.0,qodef-qi--no-touch,qi-addons-for-elementor-1.6.3,qode-page-transition-enabled,ajax_fade,page_not_loaded,,overlapping_content,qode-theme-ver-28.4,qode-theme-bridge,disabled_footer_top,qode_header_in_grid,wpb-js-composer js-comp-ver-7.1,vc_responsive,elementor-default,elementor-kit-21820

Project Progress Update (April – June 2021)

Project Progress Update

Dwi@Rimbun Kasia

This is a joint-venture initiative with Japan’s Hankyu Hanshin Properties Corp. Dwi@Rimbun Kasia is a green-living concept development comprising 382 units (53% of which are dual-key homes) aimed at the mid-market segment.

Reinforced concrete works in Block B (East Wing) have now reached Level 8 where 20 out of 26 units are completed; Level 7 was completed in December 2020. For Block A (West Wing), reinforced concrete works are completed at Level 6, with 17 out of 19 units completed at Level 7. Similarly, brick works are completed up to Level 5 for Block B and up to Level 4 for Block A.

KaMi Mont’ Kiara

This proposed 19-storey tower block comprises of 168 serviced residences with sizes ranging from 840sq ft to 1,604 sq ft is set within a private, Japanese– designed landscaped grounds. There will also be a Japanese Onsen Spa for the enjoyment of the residents. The whole development is pet friendly.

Reinforced concrete works is now complete on Levels 18 and 19 (Roof & Lift Motor Room). Architectural works (e.g. water proofing, brickworks, etc.) and M&E works (e.g. fire system, plumbing, electrics, etc.) are progressing well, including the lift shafts being handed over to the lift contractor for installation works.

ASTA Enterprise Park

ASTA Enterprise Park is a 31 acre industrial park located in the mature industrial area of Bukit Angkat, Kajang, Selangor. The freehold land has been subdivided into 46 individual titles.

Phase 1 of the development contains 18 three storey semi-detached factory units (Type A). The built up areas range from 8,594sf to 10,672sf. Phase 1 is sold out and scheduled for handover in mid-April 2021. Phase 3 (vacant plots) is also scheduled for handover in mid-April 2021.

Phase 2A of the development consists of 8, three storey semi-detached factory units with a lower ground floor (Type B). The built up area ranges from 12,375sf to 12,565sf. Piling works is currently underway and this project is targeted to be completed by November 2022.

Phase 2B of the development consists of 10 three storey semi-detached factory units with a lower ground floor (Type B). The built up area ranges from 12,375sf to 12,565sf. Earthworks is currently being done and the development is targeted to be completed in July 2023.