Project Progress Update (Oct – Dec 2020)
21314
post-template-default,single,single-post,postid-21314,single-format-standard,bridge-core-3.0,qodef-qi--no-touch,qi-addons-for-elementor-1.6.3,qode-page-transition-enabled,ajax_fade,page_not_loaded,,overlapping_content,qode-theme-ver-28.4,qode-theme-bridge,disabled_footer_top,qode_header_in_grid,wpb-js-composer js-comp-ver-7.1,vc_responsive,elementor-default,elementor-kit-21820

Project Progress Update (Oct – Dec 2020)

Project Progress Update

Dwi@Rimbun Kasia

This is a joint-venture initiative with Japan’s Hankyu Hanshin Properties Corp. Dwi@Rimbun Kasia is a green-living concept development comprising 382 units (35% of which are dual-key homes) aimed at the mid-market segment.

Reinforced concrete works have now reached Level 8 where 20 out of 26 units are completed; Level 7 where 23 out of 26 units are completed; and at Level 6 which was completed in last year.

KaMi Mont’ Kiara

This proposed 19-storey tower block comprises of 168 serviced residences with sizes ranging from 840sq ft to 1,604 sq ft is set within a private, Japanese– designed landscaped grounds. There will also be a Japanese Onsen Spa for the enjoyment of the residents. The whole development is pet friendly.

Reinforced concrete works at Level 18 is completed and Level 19 (Roof and Lift Motor room) is now in progress.

ASTA Enterprise Park

ASTA Enterprise Park is a 31 acre industrial park located in the mature industrial area of Bukit Angkat, Kajang, Selangor. The freehold land has been subdivided into 47 individual titles.

Phase 1 of the development contains 18 three storey semi-detached factory units (Type A). The built up areas range from 8,594sf to 10,672sf. Phase 1 is sold out. The physical works is complete and CCC application is in progress.

Phase 2A of the development consists of 8, three storey semi-detached factory units with a lower ground floor (Type B, B1, B2, B3). The built up area ranges from 12,375sf to 12,565sf. Piling works is currently underway and earthworks is now completed. This project is targeted to be completed by May 2022.

Phase 2B of the development consists of 10 three storey semi-detached factory units with a lower ground floor (Type B1, B4). The built up area ranges from 12,375sf to 12,565sf. Earthworks is currently being done and the development is targeted to be completed in July 2023.

There are also vacant plots available with land sizes ranging from 27,652sf to 218,152sf where physical works is completed and CCC application is in progress.

On another note, the Owners’ Association was formally registered with the Registrars of Companies and the Guarded Community Scheme was approved by the local council (MPKJ) where private security for the site is allowed.