Project Progress Update (October – December 2020)
21070
post-template-default,single,single-post,postid-21070,single-format-standard,bridge-core-3.0,qodef-qi--no-touch,qi-addons-for-elementor-1.8.1,qode-page-transition-enabled,ajax_fade,page_not_loaded,,overlapping_content,qode-theme-ver-28.4,qode-theme-bridge,disabled_footer_top,qode_header_in_grid,wpb-js-composer js-comp-ver-7.9,vc_responsive,elementor-default,elementor-kit-21820

Project Progress Update (October – December 2020)

Dwi@Rimbun Kasia

This is a joint-venture initiative with Japan’s Hankyu Hanshin Properties Corp. Dwi@Rimbun Kasia is a green-living concept development comprising 382 units (35% of which are dual-key homes) aimed at the mid-market segment.

Reinforced concrete works have now reached Level 8 where 9 out of 26 units are completed; Level 7 where 20 out of 26 units are completed; and at Level 6 which was completed in July 2020.

Architectural Works

Block B:
Brick work – Levels 1 and 2 completed, Levels 3 and 4 are in progress.
Window sub-frames – Levels 1 and 2 completed, Levels 3 is in progress.
Plaster work – Level 1 is completed, Levels 2 and 3 are in progress.
Skim coat work – Level 1 is completed, Levels 2 and 3 are in progress.

Block A:
Brick work – Level 1 is completed
Window sub-frames – Level 1 is completed

KaMi Mont’ Kiara

KaMi

This 19-storey tower block comprises of 168 serviced residences with sizes ranging from 840sq ft to 1,604 sq ft is set within a private, Japanese–designed landscaped grounds. There will also be a Japanese Onsen Spa for the enjoyment of the residents. The whole development is pet friendly.

Reinforced concrete works at Level 13 is completed and Level 14 is now in progress.

Architectural Works

Window sub-frames – Levels 5 to 8 are in progress.
Door sub-frames – Levels 5 to 8 are in progress.
Skim coat work – Levels 5 to 8 are in progress
M&E Works
Electrical and sanitary plumbing works – Levels 5 to 7 are in progress.

ASTA Enterprise Park

ASTA

ASTA Enterprise Park is a 31 acre industrial park located in the mature industrial area of Bukit Angkat, Kajang, Selangor. The freehold land has been subdivided into 47 individual titles.

Phase 1 of the development contains 18 three storey semi-detached factory units (Type A). The built up areas range from 8,594sf to 10,672sf. Phase 1 is sold out and scheduled for handover in October/ November 2020.

Phase 2A of the development consists of 8, three storey semi-detached factory units with a lower ground floor (Type B, B1, B2, B3). The built up area ranges from 12,375sf to 12,565sf. Piling works is currently underway and this project is targeted to be completed by May 2022.

Phase 2B of the development consists of 10 three storey semi-detached factory units with a lower ground floor (Type B1, B4). The built up area ranges from 12,375sf to 12,565sf. Earthworks is currently being done and the development is targeted to be completed in July 2023.

There are also vacant plots available with land sizes ranging from 27,652sf to 218,152sf.

On another note, the Owners’ Association was formally registered with the Registrars of Companies and the Guarded Community Scheme was approved by the local council (MPKJ) where private security for the site is allowed.

Sales & Marketing at Ireka

In light of the current movement restrictions in Malaysia, Ireka’s projects are being actively promoted via social media platforms, Facebook and Instagram, in particular.

We have the following accounts under Facebook and Instagram

1) propertiesbyireka (all project under Ireka)
2) rimbun.kasia (dwi Project @ nilai)

Please find below the account links:-
https://www.instagram.com/propertiesbyireka/
https://www.instagram.com/rimbun.kasia/
https://www.facebook.com/RimbunKasiaNilai/
https://www.facebook.com/PropertiesByIreka/